Project Description

The water supply system of Aybak consists of the installation 37 Km HDPE pipe with 450mm diameter for water transmission for servicing the Aybak city. The water is supplied through these pipe to a three 700M^3 water storage tanks. In addition to mentioned water storage tank, The water is supplied into 12 other 45M^3 water reservoirs by sub pipe with diameter 200mm.
The three 700M^3 water storage tanks are used for service of Aybak city and the 8 other 45M^3 water reservoirs are used for houses in the service line of water transmission.
The project items included but not limited to Chambers, Gate valve, Blow off valve, Air release valve wash out valve, Pressure breaker tank, Intake tank ,Sediment tank Water storages , HDPE pipe and Elbow.

Project Gallery

Project Description

The water supply system of Aybak consists of the installation 37 Km HDPE pipe with 450mm diameter for water transmission for servicing the Aybak city. The water is supplied through these pipe to a three 700M^3 water storage tanks. In addition to mentioned water storage tank, The water is supplied into 12 other 45M^3 water reservoirs by sub pipe with diameter 200mm.
The three 700M^3 water storage tanks are used for service of Aybak city and the 8 other 45M^3 water reservoirs are used for houses in the service line of water transmission.
The project items included but not limited to Chambers, Gate valve, Blow off valve, Air release valve wash out valve, Pressure breaker tank, Intake tank ,Sediment tank Water storages , HDPE pipe and Elbow.